DIVISION 2 - SITE WORK
GENERAL INFORMATION
-
Designate
and enforce project limits, staging areas and site access in order to limit
construction damage to areas adjacent to the construction. Refer to specific
requirements in Division 1.
-
Do not
allow parking or storage on turf areas unless approved by UNC Grounds
Department. If approved, contractor must
relieve compaction, repair damaged irrigation and replace sod as needed.
-
Define
adequate protection of trees and other plantings. This should include substantial fencing when
appropriate. Protected area should be
large enough to prevent compaction of soil within the root / drip zone. If
passage beside a tree is mandatory, a bridge shall be constructed over the root
zone of the tree and the trunk shall be protected. Do not trench within the
drip line.
WALKS, PAVING and
SURFACING
-
Sidewalks
and bike paths shall be a minimum of 6’-0” wide to allow for use of snow
removal equipment. Do not locate walks immediately adjacent to the edge of
parking lots or streets.
-
Provide
a minimum of 6’-0” radius at all intersecting walks to accommodate snow removal
equipment.
-
Layout
walks to match probable pedestrian traffic patterns in order to limit foot
traffic on planted areas.
-
Allow
space for a bicycle parking area adjacent to the main building entrance. The owner shall review the type of bicycle
rack proposed for use.
-
Provide
a concrete pad and enclosure for a trash dumpster. Dumpster pad shall be at least 6’ X 10’. If
gates are to be installed on the enclosure, they must be extremely heavy
duty. Enclosure shall be compatible with
building construction. Specify pipe bollards to protect the enclosure. Locate
bollards at the entrance to the enclosure and around the dumpster. Provide a
reinforced concrete approach pad 10’ X 10’ X 6” minimum. Locate dumpster enclosure to allow for
straight approach by the truck. Refer to
appendix drawings for dimensions of front loading trash containers and trucks
in use on campus.
-
Colored
exposed aggregate concrete has been used as an accent feature for sidewalks at
several areas on campus. The concrete is
a 4000 PSI mix, ID # P400215 from Lafarge - Greeley. 6 ½ sacks per cubic yard of concrete. 3/8”
exposed aggregate mix. Davis color
”Flagstone Brown”, 3# integral
color per sack or 19.5# of color per cubic yard.
-
Pavers
in use on West campus are generally “Medium Ironspot” as manufactured by
Pacific Clay and distributed by Lakewood Brick and Tile.
LANDSCAPING GUIDELINES
- Contactors,
designers are responsible to secure copies of the University’s Master Plan Guidelines for the Campus
Landscape and to become familiar with specifications, and standards for
tree & ornamental selection, landscape features, site furnishings and other
amenities prior to design efforts or submittals. The guidelines below do not replace or supersede,
but supplement these established university guidelines.
LANDSCAPING – TURF
- Water
conservation is a primary focus and mission at the university. It is encouraged that landscape designs
incorporate turf species mixes that tolerate drought or low water
conditions. Designs should designate a
portion of the turf to reflect this mission.
-
Do not
specify turf adjacent to buildings. Provide minimum 12” wide mowing strips to
reduce the need for hand edging and to reduce the amount of water applied
adjacent to the building. Landscaped zones adjacent to the building may also be
specified.
-
Sod used
for repair or replacement of existing sod shall match the pre-existing or
surrounding sod.
-
New sod
shall be equivalent of a ninety-nine percent improved variety blue grass sod.
A five-blend mix is recommended.
-
Areas to
receive sod shall be thoroughly scarified. Specified compost or equivalent soil
amendment shall be spread over the surface at a rate of three cubic yards per
thousand square feet. Areas shall then be tilled to a minimum of 4 to 6 inches
until no compost/amendment appears on the surface.
-
Contractor
shall be responsible for watering necessary for initial establishment of new
sod. Contractor shall also be required to maintain the sod until the time of
substantial completion of the project.
Maintenance shall include watering, mowing and rolling. Mowing to occur
at least once per week and cut to a height of 2 ½ to 3 inches.
LANDSCAPING – TREES, SHRUBS and PLANTINGS
-
Shrub
beds shall be mulched 3”-4” deep with shredded wood mulch. No gravel will be
permitted. Fabric weed barrier is
generally not required. Specify pre-emergent herbicide application prior to
installation of mulch.
-
Specify
heavy gauge steel edging for stone mulched areas only.
-
Ground
covers should be specified with close plant spacing (4-6 inch off-centered) to
allow beds to be established as quickly as possible, and in order to minimize
weed control effort.
-
Minimize
the use of small planting areas by incorporating plantings, and design planting
beds that provide an efficient mowing pattern in order to reduce trim mowing.
-
Plantings
shall not interfere with site or security lighting.
-
All
trees in lawn areas shall have a 3-4 foot diameter circle (depending on tree
diameter, ball size and tree form) of shredded wood mulch.
TREE LOCATION
Tree location shall consider the location of existing utilities, walks,
signs and lighting.
Maintain the following minimum clearances:
- 10
feet from sewer lines
- 5
feet from water, gas and electrical lines
- 6
feet (80inches) from walks and curbs.
This is not always practical or permissible, especially in Street Parkways, but
a minimum 80inch vertical clearance is required above pedestrian walks.
- Please
note:
- 15
feet from building walls (most Shade Trees), depending on species and purpose
(espalier, etc)
- Recommended
Tree spacing is 20 feet, depending on purpose, species and design.
TREE & ORNAMENTAL SELECTION
- The
University promotes species diversification. Selections should promote a variety
of non-native species, as well as
- Tree
selection should comply to University Master Plan Guidelines for the Landscape
- Street
tree plantings:
- Monoculture
Plantings are discouraged, but will be considered. Designs should consider current campus tree
density, distribution of any particular species prior to design
recommendations.
- Designs
should consider historical data of insect, disease problems on a particular
species on the campus
- Designer
should consult with the City of
- Unacceptable
trees include :
- species
of Populus genus (cottonwoods, aspens, sycamores, etc.)
- species
of Acer saccharinum (Silver Maples and cultivars thereof)
- Siberian
Elm (Ulmus pumila)
- Russian
Olive (Eleagnus angustifolia) or any cultivar thereof.
- Species
of willow (Salix genus).
- Please
Refer to City of Greeley Forestry Division Website for extensive listing of
recommended and not recommended trees http://www.ci.greeley.co.us/2/PageServiceDetails.asp?fkOrgID=48&SDID=5
- Other
Considerations:
- Soil
pH, (high alkaline 7.5-8.0) in native soils,
- Disease
and insect susceptibilities of species
- Water
conservation, Xeric-scape species, native “
SITE UTILITIES
-
Most
utilities on campus are University owned.
Coordinate all details with the owner.
-
Prior to
any excavation, all contractors shall be required to call the utility Notification
Center of
-
New
underground utilities shall be installed perpendicular or parallel to streets,
walks and building lines wherever possible.
-
Provide
16 ga. Tracer wire for all non-metallic piping. Terminate as directed by the
Owner in the field.
-
Domestic
water mains shall have a shut off valve provided at all points of take off from
mains. Valves to be CCW to open.
-
All main
water services shall be protected by an approved reduced pressure type backflow
preventer sized for full building demand.
This assembly shall also include 1” bypass with a reduced pressure type
backflow preventer.
-
Fire
hydrants shall be purchased from the City of Greeley Water Department.
-
Provide
a concrete collar at all water valve boxes.
-
Most
buildings will be required to be connected to the campus tunnel system. The tunnels generally contain high
temperature hot water mains, video cabling, telephone and data systems.
-
Telephone
systems will generally need to be extended to the main telephone switch in Gray
Hall. Data systems will be connected to
the campus fiber optic backbone. Point
of connection will be determined for each facility. The Telecommunications
Wiring Specifications are included in Division 16. All telecommunications
system must be coordinated with the UNC Information Technology Department.
-
High
voltage systems shall be in concrete encased underground duct banks with above
ground switches and transformers.
Underground vault mounted switches will be considered for certain
locations.
-
All
utility interruptions shall be coordinated through Facilities Management. Provide a minimum of 72 hours advance notice
of desired shut-downs. Provide two weeks advance notice whenever possible. Most outages will need to be performed
outside of normal working hours.
IRRIGATION SYSTEMS
(Basic requirements)
-
Water
conservation is a primary focus and mission at the university. It is encouraged that irrigation designs
incorporate innovations that encourage water conservation measures. Rain gauge, water conservation monitoring,
and master control systems are promoted. Designs should designate a portion of
the irrigation for Inline Drip Tubing (Netafim or equivalent type systems) when
practical. These systems eliminate spray
drift and water loss due to evapo-transpiration.
- Refer
to UNC suggested irrigation specification following this section.
-
Provide
PVC sleeves (minimum 4”diameter, Schedule 40 ) under all walks and drives for
irrigation piping.
-
Sprinkler
systems shall be designed to minimize sprinkler heads located in sports fields,
vehicular traffic areas or near building surfaces/foundations. System layout
shall minimize impact on pedestrian ways.
-
Verify
available water pressure prior to design. Booster pumps may be required on
systems located on Central Campus due to highly variable water pressure.
Booster pumps shall be located in a suitable enclosure.
-
Provide
quick connect fittings on main lines strategically located throughout the
site. Quick connect fittings shall be
Rain bird. Recommend 1-inch Quick couplers.
-
Mainline
piping shall be PVC schedule 40. Lateral
piping may be either Class 200 PVC or NSF 80 polyethylene. Minimum Pipe size not to be less than 1-inch.
-
All
sprinkler heads shall be attached to PVC swing joints. Swing joints shall be sealed with teflon tape
on the threads. Use of flexible type
swing joints must be approved by UNC.
-
Valve
Installation:
- When
series of valves are being “manifolded”,
installation should provide adequate pipe spacing to allow ease of repair and
replacement of valves.
- Follow
up is required to adjust valve boxes to grade after initial settling.
-
Backfilling
of sprinkler trenches shall be settled with water in all areas. Sprinklers
shall be firmly tamped under and around to ensure that they remain at grade
level.
-
Do not
locate valves or similar equipment at the intersection of walks or drives where
vehicle or cart traffic may cause damage.
-
All
splices for control wires shall be made in splice or valve boxes. Direct Bury
connections to be used.
-
Provide
at least one labeled spare control wire installed so that the wire enters and
leaves each control box.
-
Provide
warning tape buried 6” deep located over all control wiring. “CAUTION - BURIED ELECTRICAL LINE BELOW”
-
In-Line
Drip tube systems are recommended when applicable. Drip
micro-emitters type systems are not recommended.
-
Sprinkler
heads shall be manufactured by Hunter, Rainbird or Toro. “Valve-in-head”-
type sprinklers are permissible with adequate controllers and proper and practical application. Subject to prior approval by UNC Facilities
Management.
-
Control
valves shall be manufactured by Nelson or Toro.
-
Systems
are to be electrical, electrical –mechanical.
Hydraulic systems will not be considered.
-
Irrigation
controllers shall be manufactured by Constellation. Controllers shall be
pedestal or wall mounted. Controllers
should be able to provide computer master control capabilities for future application
as well as remote radio control.
-
All
wiring and piping shall be tested in the presence of the owner’s Irrigation
Technician prior to backfilling.
-
Irrigation
contractor shall winterize new sprinkler systems at the end of the first season
of operation. Owner’s Irrigation
Technician shall be present.
-
Provide
as-built drawings, O&M manuals, keys, valves keys, etc. as required in
Division 1.
-
All shop
drawings and submittals shall be reviewed by UNC Facilities Management prior to
installation.
SITE RESTORATION
-
Scarify
all planting areas for ground covers and lawns to a depth of at least 12”. Scarify in two directions. Include all areas subject to traffic during
construction.
-
Restore
and test all sprinkler systems damaged by construction.
-
The following
activities require review by the owner prior to commencement:
-
inspection
of plant materials
-
review
of amended topsoil prior to placement
-
sub-grade
examination and scarification
-
sample
stake and tie set-up
-
irrigation
testing
SITE FURNISHINGS
-
Standard
site furnishings such as benches, trash containers, tables, bicycle racks and
site lighting will be selected based on Campus Landscape Masterplan.
-
The
standard color for site furnishings and light fixtures unless otherwise noted,
is Sherwin Williams Arlington Powder Coatings.
PLS6 – 70026 UNC Norton Blue.
SIGNAGE
- All vinyl color selections are based on 3M Scotchcal Series 220 Premium film or 3M Scotchcal Series 230 translucent film as indicated.
Top blue 3M 220 Series Sapphire Blue
Bottom blue 3M 220 Series Light Navy
Yellow (logo and primary letters) 3M 220 Series Sunflower
Gray (trim and secondary letters) 3M 220 Series Medium grey
All vinyl to be 1st surface application
Paint (legs) Kwal 8773m Dauphin Grey H34
Top Blue 3M 230 Series Cobalt
(2nd surface application)
Bottom Blue 3M 220 Series** Light Navy
(2nd surface application)
Yellow (logo and primary letters) 3M 230 Series Mango
(2nd surface application, cutout)
Gray (trim and secondary letters) 3M 230 Series Silver Grey
(2nd surface application, cutout)
Paint (cabinet) Kwal 8773m Dauphin Grey H34
** Note: the bottom blue vinyl is not a translucent film.
![]()